Monday, January 27, 2020

Project plan for esso supermarket

Project plan for esso supermarket I have to create a project plan for a Deferent branch for a Esso Supermarket. This involve import all necessary hardware likes computers for check out stations, mobile barcode readers for scanning the prices and relabeling them for any reduced price offers etc. It has been said that the building infrastructure already exists and is developed by local builder. However, i need to develop a plan that incorporates all electrical, plumbing and networking. All these tasks are done by electrician, plumber and network engineer; each and every cost  £200,  £250 and  £300 a day correspondingly. Major tasks include getting the quotations from different vendors, comparing the prices and deciding the specs and vendor, ordering the checkout stations, cabling, physically installing the checkout stations, putting the LAN cables and connecting all the checkout stations to the network and finally installing all the required software for the system. I need one week to decide the specification and get it approves by our top management. Vendors usually its take two to three weeks to get you the order delivered. Assume all check out stations hardware, mobile barcode readers are supplying by one vendor. However, the air conditioning units are supplying by a different vendor and takes up to two weeks. Cabling work is done by a network engineer and installation of air conditioning units is done by a contractor. These jobs may take a maximum of 3 working days. After all hardware is in its place, all the software must be is required to be installed. This takes a maximum of 5 working days. This has done by internal IT staff member from the head office. We had already that all required software is available and ready to be installed. As the store is largest , we decided to buy 30 checkout stations, each of which include a monitor, keyboard, card (magnetic stripe) reader, bar code reader, digital weighing scale, printer, pin and chip card reader, conveyor belt system etc. Each check out station would normally cost  £1000. Twenty air conditioning units, 10 freezers to store frozen food are also necessary. Air conditioning units and freezers cost  £500 and  £750 respectively. Two security systems be installed at each of the two entrances. This cost  £1000 each unit. Hardware staff cost  £300 per day. There are 2 hardware specialists working on the project. The budget for this project is  £150,000. Base on this Scope as project manager i have to develop the Esso supermarket Period of three months if i finished early my teem get eligible to get bones 1. Identifying the most important tasks A) Collecting quotation from Various Vendors B) Compare the prices range and decide the specs C) Order the checkout station D) Plumbing E) Electrical F) LAN Cables G) Networking H) Installing all the request soft ware This main project can be divided into major 5 tasks. Under this major task there will be several sub tasks which will be executes one after another and parallel according to the project need. 1) Initiating This is the first phase of the project. Here the project formally commencing between the project sponsor and the project manager. Here first kick off meeting will be initiated here the outline of the project will be discussed and the detailed project charter will be formally developed. After developing the project charter the project manager will review the key points with project sponsor and finalise the project with project sponsor. 2) Planning Here the project planning will be started. Before the actual project implementation the project should be well planned in every area of execution. Here the project manager develop a comprehensive project plan this includes the project scope, project objectives, the project deadlines, project quality plan, project communication and project configuration plan this will be outline the roles and responsibility of the individual people. This plan will be sent to the project sponsor approval and review after make necessary changes and finally accepting the project plane. 3) Executing Here the actual project implementation starts. Before the project implementation the required hardware, software and other equipments had to be purchased. So the project behalf of the Esso supermarket is decided to develop a RFP (Request for proposal) and decided to call for the proposal from the different supplier and then review the capabilities of each supplier and then short listed some of the very famous supplier in UK. Thereafter the interview has been concluded and the final vendors are selected and the price and the after sales services arrangement were negotiated and the project contract is signed. After that the vendors are in different time periods they send all the necessary hardware and equipments to the site. The electric cable wiring and the electric circuit installations were done in the site. The main plumbing has been done from plumbers and order to install the air condition and the freezers. After that the computer local area network is done by network engineers an d all the connection were connected then the checkout stations were installed. After this the security cameras were installed at the stores. Then the required software is installed after this check the functionality with SRS and reviews any changes. Then the user or new staffs are s recruited and given the training 4) Controlling Controlling the system is done by in the way of continues status report and monitoring the progress review meetings. 5) Closing After the project is implemented the project post analysis is done and checks whether the actual project milestones were achieved 2. Identify the order the tasks (Top-to-Bottom) To setup a new superstore branch Electrical   Electric cable Wiring   Electric cable Wiring   Electric cabling designing   Freezers, Air Conditions   Computers, security cameras   Checkout Stations Purchasing Hardware Implementation Outsourcing application Analysis Design Closing Post Analysis Review Progress Review Meeting    Status Report Project Plan approved and baseline Review Project Plan Develop Project Plan Devolve project scope Controlling Develop Project Charter Kick-off meeting Charter signed Executing Review Project Charter Initiating Planning   Air condition plumbing Plumbing   Freezers Plumbing Local Area Network Designing   Local Area Network Till Installations   LAN Cable Wiring   Install Check out work stations   Implementing Application Software   Data Wiring connecting all Checkout Stations   Air Condition Installation   Installing freezers   User Acceptance Testing (UAT) Install Software Review SRS Install Security camera   2.1 Low level detail task (Finish-to-Start, Parallel) 1 Initiating 2 Kick-off meeting 3 Develop Project Charter 2 4 Review Project Charter 3 5 Charter Signed 4 6 Planning 7 Devolve project scope 5 8 Develop Project Plan (Quality, Communication, Configuration) 7 9 Review Project Plan 8 10 Project Plan approved and baseline 9 11 Executing 12 Analysis and Design 13 Prepare RFP 9 14 Sourcing 15 Call for Proposals 13 16 Review Proposals 15 17 Shortlist Suppliers 16 18 Negotiate Select Supplier 17 19 Prepare Contract 18 20 Implementation 21 Purchasing Hardware 22 Purchase Checkout Station 19 23 Purchase Computers and all other accessories 22 24 Purchase Air condition 23 25 Purchase Freezers 24 26 Purchase Security Camera 25 27 Electrical 28 Electric cabling designing 22 29 Electric cable Wiring 23 30 Electric fittings 25 31 Plumbing 32 Air condition plumbing 28 33 Freezers Plumbing 28 34 Local Area Network Till Installations 35 Local Area Network Designing 33 36 LAN Cable Wiring 35 37 Install Check out work stations 36 38 Data Wiring Connecting all Checkout Stations 37 39 Air Condition Installation 32 40 Installing freezers 32 41 Install Security System 37 42 Implementing Application Software 43 Install Software 37 44 Review SRS 43 45 User Acceptance Testing (UAT) 44 46 recruit user User Training 45 47 Controlling 48 Status Report 46 49 Progress Review Meeting with Management 48 50 Closing 51 Post Analysis Review 49 Serial Tasks or Finish-to-start Parallel Task According to above detail task the blue colour task shows the serial tasks which a particular task will start when another task is finish (Finish-Start). The yellow colour tasks are the parallel task which can be executed simultaneously at a same time. In the above question there are 5 major task been divided into sub tasks as it is shown above task list. Task number 10 11 will be parallel executed after the task 9 is completed. Task number 23 28 will be parallel executed after the task 22 is completed. Similarly the task number 26 30 will be parallel executed after the task number 25 is finished. The task 32 33 will be parallel executed similarly after the task number 28. The task 39 40 will be parallel executed similarly after the task number 32. Finally the task 41 43 will be parallel executed similarly after the task number 37. 3. Risk Matrix The following risk matrix shows the level of risk which affects the project. High R6 R2, R3 significant R5 R8 Moderate R7 R1, R4 Low R10 Probability Low Moderate Significant High Impact Risk = probability x impact R1: Inefficient staff R2: Shortfalls in externally supplied equipments R3: Staff sickness affecting critical activities R4: Shortfalls in contract employed staff R5: Failure of checkout workstation R6: Failure of electricity network R7: Failure of Local area Network equipment R8: Staff unhappy with the payment. R9: Defect in Software Application R10: Mistake in Plumbing design 4. Total Time taken to finish the superstore to up and operational Initiating 5d Mon 06/09/10 Fri 10/09/10 Project preparation 1d Mon 06/09/10 Mon 06/09/10 Develop Project Charter 1d Tue 07/09/10 Tue 07/09/10 Review Project Charter 1d Wed 08/09/10 Wed 08/09/10 Charter Signed 2d Thu 09/09/10 Fri 10/09/10 Planning 9d Mon 13/09/10 Thu 23/09/10 Devolve project scope 3d Mon 13/09/10 Wed 15/09/10 Develop Project Plan (Quality, Communication, Configuration) 2d Thu 16/09/10 Fri 17/09/10 Review Project Plan 2d Mon 20/09/10 Tue 21/09/10 Project Plan approved and baseline 2d Wed 22/09/10 Thu 23/09/10 Executing 51d Fri 24/09/10 Fri 03/12/10 Analysis and Design 4d Fri 24/09/10 Wed 29/09/10 Prepare RFP 4d Fri 24/09/10 Wed 29/09/10 Sourcing 9d Thu 30/09/10 Tue 12/10/10 Call for Proposals 1d Thu 30/09/10 Thu 30/09/10 Review Proposals 1d Fri 01/10/10 Fri 01/10/10 Shortlist Suppliers 1d Mon 04/10/10 Mon 04/10/10 Negotiate Select Supplier 3d Tue 05/10/10 Thu 07/10/10 Prepare Contract 3d Fri 08/10/10 Tue 12/10/10 Implementation 37d Wed 13/10/10 Thu 02/12/10 Purchasing Hardware 28d Wed 13/10/10 Fri 19/11/10 Purchase Checkout Station 5d Wed 13/10/10 Tue 19/10/10 Purchase Computers and all other accessories 1w Mon 01/11/10 Fri 05/11/10 Purchase Air condition And all other accessories 3d Mon 08/11/10 Wed 10/11/10 Purchase Freezers And all other accessories 3d Thu 11/11/10 Mon 15/11/10 Purchase Security System and all other accessories 4d Tue 16/11/10 Fri 19/11/10 Electrical 24d Wed 20/10/10 Mon 22/11/10 Electric cabling designing 5d Wed 20/10/10 Tue 26/10/10 Electric cable Wiring 2w Mon 08/11/10 Fri 19/11/10 Electric fittings 5d Tue 16/11/10 Mon 22/11/10 Plumbing 7d Wed 27/10/10 Thu 04/11/10 Air condition plumbing 5d Wed 27/10/10 Tue 02/11/10 Freezers Plumbing 3d Wed 27/10/10 Fri 29/10/10 Aircondition cabling 2d Mon 01/11/10 Tue 02/11/10 Freezer cabling 2d Wed 03/11/10 Thu 04/11/10 Local Area Network Till Installations 27d Wed 27/10/10 Thu 02/12/10 Local Area Network Designing 1d Fri 05/11/10 Fri 05/11/10 LAN Cable Wiring 5d Mon 08/11/10 Fri 12/11/10 Install Chck out work stations 5d Mon 15/11/10 Fri 19/11/10 Data Wiring Connecting all Checkout Stations 5d Mon 22/11/10 Fri 26/11/10 Air Condition Installation 3d Wed 27/10/10 Fri 29/10/10 Installing freezers 3d Wed 27/10/10 Fri 29/10/10 Install Security System 4d Mon 29/11/10 Thu 02/12/10 Implementing Application Software 10d Mon 22/11/10 Fri 03/12/10 Install Software 5d Mon 22/11/10 Fri 26/11/10 Review SRS 2d Mon 29/11/10 Tue 30/11/10 User Acceptance Testing (UAT) 2d Wed 01/12/10 Thu 02/12/10 recruit user User Training 1d Fri 03/12/10 Fri 03/12/10 Controlling 2d Mon 06/12/10 Tue 07/12/10 Status Report 1d Mon 06/12/10 Mon 06/12/10 Progress Review Meeting with Management 1d Tue 07/12/10 Tue 07/12/10 Closing 1d Wed 08/12/10 Wed 08/12/10 Post Analysis Review 1d Wed 08/12/10 Wed 08/12/10 According to the working the super store will be finished and up and running on the 24th of Dec2010. This date is well inside the 3 month target period. 5) Establish the labour costs and provide a work breakdown structure and contain these costs. The WBS have to contents a estimates and mirrored on the work breakdown structure and have to be capable of rolling-up to show the overall cost of the project and the individual cost of each sub deliverables Develop a work breakdown structure for the hardware tasks which have tangible outcoming and a (PBS) process breakdown structure for those tasks which are process oriented. We can link the two structures, i.e. WBS and PBS so one project manager can manage the project or do you have other suggestions? The Total Labour Cost for this Project  £ 53,400 All Details Attach on Appendix 1 The Total Materials Cost for this Project  £ 51,500 All Details Attach on Appendix 2 Total Direct cost  £ 104,900 Assuming the Direct Overhead cost and General and Administration Cost from the total Direct cost Total Direct Cost  £ 104,900 Direct Over head cost 20%  £ 20,980 Total Direct Cost  £ 125,880 General and administrative (GA) over head cost 20%  £ 20,980 Total Cost  £ 146,860 Profit  £ 3,140 Total BID  £ 150,000 5. Work Breakdown Structure (WBS) 5.1 Labour Cost WBS Labour Cost  £ 53,400 Air Condition Installation  £ 2000 Contractor  £2000 Install Security System  £ 600 Installing freezers  £ 600 LAN Cable Wiring  £ 1200 Air condition plumbing  £1200 Electric cable wiring  £3000 Hard Ware Staff  £6600 Install Check out work stations  £ 4200 Install Security System  £ 1200 Data Wiring  £ 8400 LAN Cable Wiring  £ 6000 Local Area Network  £ 600 Freezers Caballing  £ 1200 Air condition caballing  £ 1200 Net work Engineer  £ 25200 Plumber  £6000 Freezers Plumbing  £3000 Air condition plumbing  £ 3000 Install Security camera  £ 400 Data Wiring  £ 800 Electric fittings  £ 3200 Electric cabling designing  £ 1600 Electric cable wiring  £ 7200 Electric cabling designing  £ 1600 Electrician  £13600 Hard Ware Task 5.2 Hardware WBS Install Security System Install Security System LAN Cabling LAN Cable Wiring Freezers Plumbing Freezer Cabling Air-condition Air condition plumbing Electric cable Wiring A/C Electric Cabling Freezers pipe lining Pipe lining to A/C Electric cable Wiring Freezer Fixing The Security System on suitable place Under Floor LAN Lining Electric cable wiring for Check out station 6. Develop a project plan using Project 2007 6.1 WBS using Project 2007 6.2 GANN Chart using Project 2007 6.3 Network Diagram using Project 2007 7. Organisational Breakdown Structure (OBS) The OBS provides an organizational rather than a task-based perspective of the project.   The hierarchical structure of the OBS allows the aggregation of project information to higher levels when project responsibilities are defined. An OBS might include the Project Manager at the top of the structure with Internal IT team, Building team l feeding into the Project manager. Each of the responsible team would have staff/staffs responsible for that organization. Pictorially, the structure might resemble this. This Performing Department level is where the responsibility and resources needed to accomplish. Project Manager Internal IT Team Tea Building Team Electrical Staff Tea Plumbing Staffs Tea Software staffs Tea Hardware Staffs Tea Network staff Tea 8. Critical path analysis The critical analyse made from Project 2007 the following red colour task were shown in the Gann chart. The Critical Path is follows as Kick-off meeting -> Develop Project Charter -> Review Project Charter -> Charter Signed -> Devolve project scope -> Develop Project Plan -> Review Project Plan -> Project Plan approved and baseline -> Prepare RFP -> Call for Proposals -> Review Proposals -> Shortlist Suppliers -> Negotiate Select Supplier -> Prepare Contract -> Purchase Checkout Station -> Electric cabling designing -> Freezers Plumbing -> Air-condition cabling -> Freezer cabling -> Local Area Network Designing -> LAN Cable Wiring -> Install Check out work stations -> Install Software -> Review SRS -> User Acceptance Testing (UAT) -> Status Report -> Progress Review Meeting with Management -> Post Analysis Review Main Problem is in the task number between 22 and 26. If the outside vender is not supply the equipment then the whole project will get delay 9. Responsibility matrix. The following matrix shows the responsibly of each Role and Responsibilities: Project Sponsor Project Manager System Engineer Network Engineer IT executive Plumbing staff Electrical staff Allocation of funds R P Overall supervision P Project Management R Analysis Design p   p Plumbing R Electricity cabling R   R Purchasing Hardware   R R P P Data/Power Wiring Hardware Installation R R R R R R Implementing Application Software R R R R R R Status Report P R R Quality Assurance R R R R R R R R R R R Acceptance   R P P Responsibility -R Participation -P 10. Reference Kamaran Saqib(2008), Class Notes. Clifford F. Gray and Erik W.Larson(2008), Project Management, the managerial process, (4th edn), McGraw-Hill International Edition. Schwalbe K.(2005), Information Technology Project Management, (4th edn), Thomson course technology. Appendix Appendix 3 Building planning Air Conditions Check out station Security System Freezers Network Cabling and Electric Caballing Plumbing and Electric Caballing 4 8 10 9 2 1 7 6 5 4 3 2 5 3 6 7 14 15 11 10 8 4 188 19 21 1 30 29 28 27 26 25 24 23 22 20 17 16 12 8 1 2 3 5 6 7 8 9 3 1 9 11 12 13 1000 2 4 14 15 16 20 19 18 17 4 14 15 11 10 188 19 21 30 29 28 27 26 25 24 23 22 20 17 16 12 8 1 2 3 5 6 7 8 9

Sunday, January 19, 2020

A Look into the Watergate Affair Essay -- Politics American History Ri

A Look into the Watergate Affair The Watergate Affair, is the worst political scandal in U.S. history. It led to the resignation of the president, Richard M. Nixon, after he became implicated in an attempt to cover up the scandal. â€Å"The Watergate Affair† refers to the break-in and electronic bugging in 1972, of the Democratic National Committee headquarters in the Watergate apartment, and office building complex in Washington D.C. The term was applied to several related scandals. More than thirty administration officials, campaign officials, and financial contributors pleaded guilty or were found guilty of breaking the law. Nixon faced possible indictment after his resignation, received from his successor, Gerald Ford, a full pardon for all of his offenses he may or had committed (Branford 2). In 1971, Nixon created the Special Investigation Unit, know as the â€Å"plumbers†, their job was to plug all new leaks. Later that year, his agents broke into the office of Dr. Lewis Feilding, and Dr. Daniel Ellsberg, who had given copies of the Pentagon Papers, a secret account of U.S. involvement in Indochina, to newspapers. After Nixon learned of the break-in, he and his top advisors decided to say that the break-in had been carried out for naitonal security reasons(Watergate 3). Later in 1971, H.R. Haldeman, Nixon’s chief of staff, was notified by an assistant, Gordon Stachan, that the U.S. Attorney General John Mitchell and John Dean, counsel to the president, had discussed the need to develop a â€Å"political intelligence capability† at the Committee for Reelection of the President(CRP). Some of the personnel and tactics identified with the activities became associated with efforts aimed at the Democrats. In early 1972, Mitchell assumed a new positio n as director of the CRP and discussed political espionage plans with Dean. Mitchell also provided the proposal to break-in to the Watergate(Branford 3). On June 17, 1972, police arrested five men at the DNC headquarters. The men were adjusting electronic equipment that they had installed in May. One of the men arrested was James McCord, security coordinator for the CRP(Watergate 3). Ehrlichman was ordered to destroy incriminating documents and tapes. Then L. Patrick Gray resigned as acting director of the FBI, later admitting he had destroyed documents given to him by Ehrlichman and Dean. On June 23, 1972, Nix... ...dited version that Nixon would submit to the Grand Jury and to the Senate. One tape contained an 18 minute gap, that gave confusing testimony on how the gap might have occurred. Electronic experts found that someone must have deliberately destroyed evidence. On March 1, 1974 seven former aides to the president; Haldeman, Ehrlichman, Mitchell, Colson, Strachan, Robert Mardian, and Kenneth Parkinson, were indicted for conspiring to hinder the Watergate investigation. Colson pleaded guilty, and Strachan’s charges were dropped. The remaining five went on to trial in October 1974 and January 1, 1975, all but Parkinson were found guilty. In late July the House committee approved three articles of impeachment(Carson 2). Shortly thereafter James St. Clair, the president’s lawyer, learned that one of the 64 tapes that Nixon had been compelled to surrender was the June 23, 1972, conversation with Haldeman in which Nixon sought to thwart the FBI investigation. He insisted that Nixon publish the tape. Nixon did so, and his support in congress virtually disappeared. Facing certain impeachment and removal from office, Nixon resigned, effective at noon August 9, 1974(Watergate 4).

Saturday, January 11, 2020

Critical Analysis of a Passage from Homer’s The Odyssey Essay

I. This passage comes very early in the Telemachy and it is wholly descriptive. The first point of interest is the arrival of Athene to Telemachos’ home in Ithaca. Disguised as Mentes’, leader of the Taphians and an old friend of Odysseus. Telemachos is the first to greet Athene as it would appear all the servants are busy working for all of the suitors. The main part of the passage is Telemachos trying to offer traditional guest hospitality customs but also attempting to keep the guest from the overbearing, rowdy suitors â€Å"For himself, he drew a painted bench next her, apart from the others, the suitors, for fear the guest, made uneasy by the uproar, might lose his appetite there among the overbearing people† 1.131-35. II. The first point to note is Telemachos clear effort to observe the hospitality customs to the best of his ability despite the mitigating circumstances of the suitors’ invasion of his home. He appears to be trying to lavish his guest with the best he has and what has been left to him, after the suitors’ abuse of his home and possessions â€Å"the chair splendid and elaborate†, â€Å"For himself, he drew a painted bench† 1.131 and 32. This is obvious here in what he offers his guest and what he takes for himself. Another example of the theme of hospitality we see is evident in these lines â€Å"golden pitcher†, â€Å"silver basin† and â€Å"polished table† 1.136 and 37. Only the finest for his guest. Now what has been clear leading up to this passage and the context of Book 1, is the encroachment of the suitors’. Telemachos does not want to make his guest uncomfortable, but concurrently has another motive for leading Athene/ Mentes’ away from the raucous of the suitors â€Å"and so he might also ask him about his father† 1.135. Even after 2o years of his father’s absence, Telemachos is still holding onto the hope of hearing news of his father, despite the general belief of his people that his father is dead. Nevertheless, given the desperate situation Telemachos and Penelope are in, this hope is understandable. One important feature to be aware of is the author’s heavy use of nouns and epithets â€Å"overbearing people†, â€Å"absent father†, â€Å"grave housekeeper† and â€Å"haughty suitors† 1.34, 35, 39 and 44. He uses words such as overbearing, absent and haughty, to convey the feelings and behaviour of the characters and also the current situation in just a few words. III. Overall, Book 1 sets out the story with some background given. It sets the tone and the mood in the Telemachy as quite sombre and desperate for Odysseus’ family at home awaiting any news of their loved one. It also puts forward an almost desolate need for Odysseus’ return home. The passage itself is a clear example of the theme of hospitality that is a predominant feature of Books 1 – 4. It contrasts Telemachos’ observance of the hospitality customs with the suitors of abuse of these customs.

Friday, January 3, 2020

Individualism and Democracy in America - Free Essay Example

Sample details Pages: 2 Words: 581 Downloads: 1 Date added: 2019/02/15 Category Politics Essay Level High school Topics: Democracy Essay Did you like this example? Democracy was formulated as a governance approach to address the needs of different population groups. However, individualism in the society has overlooked this intended purpose whereby the needs of the majority poor are often ignored as they are of no financial gain both to the government and businesses. The author highlights a common practice by most businesses, the formulation or offering support to political positions that are contrary to the preferences of the democratic majority. Don’t waste time! Our writers will create an original "Individualism and Democracy in America" essay for you Create order By using an example on how businesses often ignore these preferences for individualistic business gains, it can be acknowledged that government policies are formulated not to favor the preferences of the citizens, but rather the business groups. The author’s remarks are a true reflection of the happenings in today’s society. Businesses rarely propagate the enactment of policies that support the interest of the majority but are inclined towards those that address their needs. The use of an example on how a different situation might have elicited a dissimilar opposition emphasizes on the aspect that, when the government officials articulate policies, they serve the interest of the business instead of that of the public. Therefore, this is an actual replica of the happenings in the individualistic, democratic American society. Notably, rhetorical questions have been used in the article to emphasize the author’s point of view and get the audience thinking. This is an effective approach to influence the readers as it elicits interest on the subject matter. This is followed suit by a compressive discussion on the tactical approach deployed by businesses, â€Å"advertorials,† to preserve their advantaged position. Through this, the article emphasizes on how businesses tend to equate real societal issues with democracy while silencing issues that might raise questions regarding their privilege. For example, gun lobbyists in America today have highlighted the need for possessing assault rifles in the name of â€Å"personal protection† despite the danger it poses by equating it to their democratic right. With this, it can be acknowledged that increased emphasis on individualism has heightened the reluctance to address wider political issues that are of importance to the general so ciety. The sense of individualism has increased the emphasis on reduced political participation. The article addresses this American culture by highlighting varying reasons that have in the past been used to propagate this practice. Indeed, the Americans are reluctant to participate in politics on the notion that it has little influence on their lives. Despite this, it can be acknowledged that their material well-being is highly dependent on political involvement. For instance, it the 2012 elections, there was a turnout rate of approximately 53% thereby highlighting the problematic nature of the individualist culture. According to the article, this is enhanced by the interest of having benefits distributed through the marketplace instead of political policies. The use of the example of the U.S healthcare system highlights on how this culture intensifies bias. To negate these practices, group-based affiliations have formed the basis of American politics. However, this too works a t the disadvantage of the lower-class Americans. By highlighting on this bias, the author reflects on the current situation in the American system whereby the highly disadvantaged people are the lower class. While the higher class has their share in policy formulations, these groups have been subjected to significant disadvantages. To emphasize on this issue, the article highlights on the American labor unions and compare them to that of Sweden from which this practice of bias can be admitted to be in existence.